Fast Track Permitting

building
Fast Track Permitting

Huntley’s permitting process provides for fast permitting and development approvals. Fast tracking demonstrates Huntley's understanding that time is money. Efficient and timely approvals minimize construction related costs and represent an important economic advantage.

 Qualified sites are parcels:

  • listed for sale or lease 
  • appropriately zoned
  • meet zoning and comprehensive plan requirements
  • served by utilities
  • fulfill the requirements of the development application 
  • maintain access to existing road networks

Properties with these characteristics allow a business to receive plan approvals within 90 days of full plan submittal.

 Recent examples of fast track permitting approval include: 

Facility Type

Size

Approval Time

Distribution/Warehouse

757,000 SF

85 Days 

Supportive Living Center

118,000 SF

62 Days

Stand Alone Retail

16,000 SF

70 Days

Stand Alone Retail

8,000 SF

72 Days

Stand Alone Retail Redevelopment

5,700 SF

43 Days

Warehouse Expansion

20,000 SF

48 Days

Distribution Center

42,000 SF

43 Days

Retail Build-out

 Various

31 Days

Retail Build-out

 Various

24 Days

Retail Build-out

 Various

37 Days

Source:  Village of Huntley, Development Services Department