Huntley’s permitting process provides for fast permitting and development approvals. Fast tracking demonstrates Huntley's understanding that time is money. Efficient and timely approvals minimize construction related costs and represent an important economic advantage.
Qualified sites are parcels:
- listed for sale or lease
- appropriately zoned
- meet zoning and comprehensive plan requirements
- served by utilities
- fulfill the requirements of the development application
- maintain access to existing road networks
Properties with these characteristics allow a business to receive plan approvals within 90 days of full plan submittal.
Recent examples of fast track permitting approval include:
Facility Type |
Size |
Approval Time |
Distribution/Warehouse |
757,000 SF |
85 Days |
Supportive Living Center |
118,000 SF |
62 Days |
Stand Alone Retail |
16,000 SF |
70 Days |
Stand Alone Retail |
8,000 SF |
72 Days |
Stand Alone Retail Redevelopment |
5,700 SF |
43 Days |
Warehouse Expansion |
20,000 SF |
48 Days |
Distribution Center |
42,000 SF |
43 Days |
Retail Build-out |
Various |
31 Days |
Retail Build-out |
Various |
24 Days |
Retail Build-out |
Various |
37 Days |
Source: Village of Huntley, Development Services Department